MORPETH SCHOOL

BEFORE
DURING
PROJECT DETAILS

Project: Conversion of Kitchen to Library

Client: Morpeth School

Location: Morpeth School - Wessex Campus

Duration: 6 weeks


Value: £ 122,000

PROJECT DESCRIPTION

Strip out of the existing kitchen facility and conversion into a library

Isolation & removal of redundant kitchen equipment, removal of floor wall & ceiling finishes back to a shell. Relining of walls. New lighting & power. New HRV system with BMS controls. Removal of existing roller shutters & installation of new sound proof doors & screens. Complete redecoration & floor finishes

AFTER